First, go to https://control.openpath.com/login and log in. To access the European Control Center, please go to https://control.eu.openpath.com/login.

To assign a Schedule to a Group:

  1. Under Users > Groups select a Group or click the plus(+) on the top right to create a new Group.

  2. Under the Access column, use the sliders to give access to Entries and Zones.

  3. After giving access, you have the option to use the dropdown under the Group Schedule column.

  4. From the dropdown, select a Schedule.

  5. Click Save.

To assign the created Schedule to a User:

  1. Under Users > Users select a User or click the plus(+) on the top right to create a new User.

  2. Go to the Access tab.

  3. Under the Access column, use the sliders to give access to Entries and Zones.

  4. After giving access, you have the option to use the dropdown under the User Schedule column.

  5. From the dropdown, select a Schedule.

  6. Click Save.